What does this mean for freight buyers?
The 12.87% national truckload rejection reading is a reason to check your routing guide, not a multiplier for your lane rates. For each important lane, estimate how many loads your primary carrier will accept and what it costs to cover the loads they turn down. A lower bid is only cheaper if the carrier accepts enough freight at that price.
What changed?
In a November 18 FreightWaves report ↗, SONAR put its national spot linehaul index at $2.60 per mile and its dry-van contract base-rate measure at $2.88 per mile as of November 13. Both exclude fuel. They describe different pools of freight and are not quoted alternatives for a specific origin, destination, date or shipper.
The same report put the national truckload rejection index at 12.87% and counted 1,551,161 tractors in for-hire fleets, approximately 107,000 fewer than a year earlier. FreightWaves said new registration-system changes could account for some of the recorded decline. Treat it as a decline in the series, not an independently verified number of trucks taken off the road. Regional rejections also differed materially: SONAR reported 23.19% in the Northwest and 17.55% in the Midwest.
Budget the freight your primary carrier won't take
SCS analysis. Use your own next bid's all-in lane quotes and recent acceptance by lane, equipment, pickup day and notice period. Ask alternates how many loads they can actually cover. Do not use the 12.87% national reading as a default acceptance forecast.
Worked example: 40 equivalent loads on one 500-mile lane. All rates, acceptances and costs in this illustration are fictional, and rates include fuel on the same basis. Accessorials and late-delivery costs are omitted.
- Lower headline bid at $1,475/load: Primary coverage: 35 × $1,475 = $51,625; Backup coverage: 5 × $1,750 = $8,750; Total for 40 loads: $60,375
- Firmer award at $1,500/load: Primary coverage: 39 × $1,500 = $58,500; Backup coverage: 1 × $1,750 = $1,750; Total for 40 loads: $60,250
In this scenario, the higher primary price costs $125 less overall. The lower bid starts at $59,000 if all 40 tenders are accepted; each replacement adds $275. Four replacements would cost $60,100, but five cost $60,375. At that fifth fallback, the award preference flips under these assumptions. Use the same test for your own lanes and service floors.
What to check before awarding the lane
- Export accepted and rejected tenders by lane and day. Separate awarded loads never offered to the carrier from tenders it actually turned down.
- Put primary and backup costs on matching fuel, mileage, detention and appointment assumptions. Identify which price is firm and which is a forecast.
- Get the carrier's supported weekly load count and notice requirement in writing. Retain a secondary carrier for critical loads if primary and backup coverage both look thin.
- Decide what to monitor after award: acceptance rates, number of fallbacks, and the all-in cost of fallback loads.
Frequently asked questions
Does 12.87% mean that 12.87% of my loads will be rejected?
No. It is SONAR's national reading for contracted tender rejections. Your exposure depends on your lanes, carriers, equipment and booking windows.
Should I replace a $2.88 contract rate with the $2.60 spot figure?
Not on these figures alone. Compare executable lane quotes with matching service, fuel, pickup and accessorial terms. The indexes do not price your shipment.
Does this establish what 2027 contracts will cost?
No. This is a dated market snapshot and a way to test a budget, not a forecast for your annual award.
Sources & publication notes
- FreightWaves / SONAR, November 18 ↗ — data publisher's public article was read. It supports the November 13 rate snapshots, national and regional rejection readings, tractor series and registration caveat. Paid underlying series were not accessed or independently reproduced.
- Earlier SCS holiday truckload and fuel coverage ↗ — related context; not a second source for SONAR data.
- Prepared by the SCS Editorial Desk with AI-assisted source checking and original analysis. The routing-guide comparison is synthetic. No separate human factual review is recorded. Research edition: November 18, 2026 Pacific. Publication and update timestamps are shown above.
November 18 Pacific evening owner-authorized update. Reporting, conditional exposure and original decision aids are distinct; original publication dates retained for existing articles.
Sources & publication notes
Source-linked reporting; figures remain attributed, not independently audited. Source dates and limits appear in the article. Operational, commercial and regulatory conditions may change.
- November 18 FreightWaves report ↗Source dates identified in article; checked November 18, 2026 Pacific · Attribution and verification limits appear in the article.
SCS publication: 19 Nov 2026 · 03:12 UTC. Last modified: 19 Nov 2026. Research cutoff: 2026-11-19T03:12:38Z; not the publication time. Source dates are distinct from publication. Reported figures remain attributed, not independently audited. External source availability may vary.
Prepared with AI-assisted research and original analysis. Owner authorized publication; a separate human factual review is not recorded.
Use your own evidence.
Compare complete shipment costs ↗ — Use matched written offers and explicit assumptions.
Review freight costs and evidence ↗ — Use booking, invoice and contract evidence.
Tools remain separate from the reporting. No headline becomes a live quote, a guaranteed saving or an automatic surcharge.